What is the Notified Sum under the Construction Act?

By George Kershaw, Founder, ContraUpdated

The Notified Sum is the amount of money that becomes due for a payment cycle under the Housing Grants, Construction and Regeneration Act 1996. It is the sum stated in the payer's Payment Notice under s.110A; where the payer serves no Payment Notice, the subcontractor's Application for Payment stands as the default payment notice and its figure becomes the Notified Sum. Under s.111 that sum must be paid in full by the final date for payment unless the payer served a valid Pay Less Notice reducing it beforehand.

Key takeaways

  • The Notified Sum is the figure the payer is legally bound to pay for a given cycle, not a negotiating position.
  • It is fixed either by the payer's s.110A Payment Notice or, if none is given, by the subcontractor's Application for Payment.
  • Under s.111 it must be paid in full by the final date for payment unless a valid Pay Less Notice reduced it in time.
  • No valid Pay Less Notice means the whole Notified Sum falls due and is enforceable in adjudication.

The statutory definition

The Notified Sum is a creature of statute. It comes from the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act), as amended by the Local Democracy, Economic Development and Construction Act 2009. For every payment cycle in a construction contract the Act requires a sum to be identified as due. That figure is the Notified Sum. It is not the amount the main contractor thinks is fair, nor the amount that survives a later valuation dispute. It is the amount the Act says must be paid for that cycle, and it is fixed by the notice regime, not by argument.

How the sum is fixed

Section 110A sets the primary route. The payer must give a Payment Notice within five days of the due date, stating the sum the payer considers due and the basis for it. If the payer gives that notice, the sum stated in it is the Notified Sum. The point of the notice is precision: it commits the payer to a figure early and in writing.

The Act then closes the gap the payer is most tempted to exploit. If the payer serves no Payment Notice, the subcontractor's Application for Payment stands as the default payment notice, and the sum applied for becomes the Notified Sum. Silence does not delay payment. It hands the subcontractor the number. A well-drafted Application for Payment is therefore not merely a request; where the payer fails to respond it is the instrument that fixes the debt.

Section 111: paid in full unless displaced

Section 111 is where the Notified Sum bites. It provides that the payer must pay the Notified Sum in full by the final date for payment. The only way to pay less is to serve a valid Pay Less Notice before the final date for payment, stating the reduced sum and the basis for the reduction. Under the Scheme for Construction Contracts the Pay Less Notice must be given not later than seven days before the final date for payment.

The Payment Notice and the Pay Less Notice are distinct instruments doing distinct jobs. The Payment Notice fixes the sum at the start of the cycle. The Pay Less Notice is the payer's only route to pay a smaller amount at the end of it. Conflating the two is a common and expensive error. If the payer serves no valid Pay Less Notice, there is nothing to displace the Notified Sum, and the whole of it falls due.

Why it is the central concept for enforcement

The Notified Sum is the concept everything else in payment enforcement turns on, because it converts a valuation into a debt. Once the sum is notified and the final date for payment passes without a valid Pay Less Notice, the subcontractor is not owed an arguable claim; it is owed a fixed number the payer was obliged to pay. That is what makes it enforceable.

  • It replaces a contested account with a single figure the payer is bound to.
  • It removes the payer's ability to re-argue valuation after the deadline has passed.
  • It gives the adjudicator a clean question: was the Notified Sum paid in full, and if not, was a valid Pay Less Notice served in time.
  • It underpins the smash-and-grab adjudication, where the only issue is the unpaid Notified Sum.

Section 108 lets a subcontractor refer a dispute to adjudication at any time. The adjudicator must reach a decision within 28 days, and that decision is binding and immediately enforceable; the courts summarised the position in Macob v Morrison as pay now, argue later. Where the payer served no valid Pay Less Notice, the enforcement is brutally simple: the Notified Sum was due, it was not paid, and the adjudicator orders it paid. Any dispute about the true value of the work is left for another day and does not delay the cash.

Fixing the sum in practice

Knowing the law is not the same as holding the evidence. When the deadline lapses, the subcontractor must be able to show, to the day, what was applied for, what notice the payer gave or failed to give, and when the final date for payment fell. Late payment already stretches subcontractor days sales outstanding to 65 to 80 days, and with 3,827 UK construction firms going insolvent in the twelve months to March 2026, specialist subcontractors more than half of the monthly count, the record either exists on the day the money crystallises or it does not exist at all.

Contra is built for exactly that. The Register™ tracks every live Application for Payment across every main contractor. The Clock™ runs the statutory countdown on each notice, so the payer's five days and the seven-day Pay Less window are watched, not guessed. When a deadline lapses with no valid Pay Less Notice, that becomes Crystallised Entitlement™: the Notified Sum is now the sub's to force, and The Record™ holds the dated, signed, admissible trail an adjudicator needs. Draw Forward™, advancing a Notified Sum the same day it crystallises, is coming. Request access.

This guide is general information on UK construction payment law, not legal advice. Payment terms vary by contract; take advice on your specific position.

About the author

George Kershaw · Founder, Contra

George Kershaw is the founder of Contra, which builds Construction Act payment and deadline tracking for UK specialist subcontractors. He writes on subcontractor payment rights, the Housing Grants, Construction and Regeneration Act 1996, and construction adjudication.

Sources

Frequently asked

Is the Notified Sum the same as the amount in my Application for Payment?

Only when the payer serves no Payment Notice. If the payer gives a valid s.110A Payment Notice, the sum in that notice is the Notified Sum. If the payer stays silent and gives no Payment Notice, your Application for Payment becomes the default payment notice and the sum you applied for becomes the Notified Sum.

Can the main contractor reduce the Notified Sum after it is fixed?

Only by serving a valid Pay Less Notice before the final date for payment, stating the reduced sum and the basis for it. Under the Scheme this must be given not later than seven days before the final date for payment. Without a valid Pay Less Notice served in time, the full Notified Sum is due and cannot be cut down after the deadline.

What happens if the payer misses the final date for payment without a Pay Less Notice?

The whole Notified Sum falls due as a debt. You can refer the non-payment to adjudication at any time under s.108, and the adjudicator must decide within 28 days. The decision is binding and enforceable on a pay now, argue later basis, so the money is paid first and any valuation dispute is dealt with later.